Each box is an activity; the number it contains is the duration of the activity

Each box is an activity; the number it contains is the duration of the activity in days. The duration of the critical path is(75)

A.16days

B.14days

C.19days

D.20days

正確答案:

C解析:關鍵路徑為最長時間的線路,3+6+7+1+2=19。